Earned value management (EVM) gives owners a way to compare the work that should have been completed, the work actually accomplished, and the cost incurred to accomplish it. I use those relationships to challenge forecasts before overruns become unavoidable. The value is not in producing another dashboard. It is in establishing a credible baseline, demanding evidence of progress, and using performance trends to decide where intervention is necessary.
Spending the budget is not delivering the project
When a monthly report tells me that a project has spent 40% of its budget and is 40% complete, my first question is what the project was supposed to have accomplished by that date. My second is how completion was measured. If the answer to either question is uncertain, the apparent alignment between spending and progress offers little comfort.
Even when both percentages are reliable, they only establish cost efficiency to date if they use the same budget and scope. They do not establish whether the project is on schedule or whether the remaining work can be delivered for the available money.
A project can look financially healthy while deferring difficult installation, integration, testing or turnover activities. It can also appear underspent because invoices are late or because the contractor has not mobilized the resources needed to maintain the schedule. Neither condition is a saving.
I want a report that separates these issues rather than combining them into one favorable status color. A CFO needs to see the potential funding exposure. A delivery leader needs to see which work is falling behind. Both need to know whether corrective action is credible.
The measures an owner needs to understand
Earned value uses the approved budget as a common unit of measurement for planned and completed work. That does not mean completed work has generated revenue or that its market value equals its budget.
The GAO Cost Estimating and Assessment Guide, published in March 2020, defines cost and schedule performance indices as ratios of budgeted accomplishment to actual cost and planned accomplishment, respectively (Table 23, page 257). GAO writes mainly about federal programs, but says its best practices are equally applicable to capital and non-capital projects, including federal construction and maintenance work. It is guidance, not a mandatory private-sector standard.
| Measure | Meaning |
|---|---|
| Budget at completion (BAC) | Total approved performance budget for the measured scope |
| Planned value (PV) | Budget assigned to work scheduled through the status date |
| Earned value (EV) | Budget assigned to work actually accomplished through that date |
| Actual cost (AC) | Cost incurred for the measured work through that date |
| Cost variance (CV) = EV − AC | Negative means the work cost more than its budgeted value |
| Schedule variance (SV) = EV − PV | Negative means less budgeted work was accomplished than planned |
| Cost performance index (CPI) = EV / AC | Below 1.0 indicates unfavorable cost efficiency |
| Schedule performance index (SPI) = EV / PV | Below 1.0 indicates less budgeted accomplishment than planned |
The indices are dimensionless. Schedule variance is expressed in budget units, not days. Where a denominator is zero, the corresponding ratio is undefined; it should not be reported as perfect performance.
A worked example
The following uses illustrative, hypothetical figures, not a client result. Assume a single measured scope with a $100 million BAC. At the reporting date, PV is $50 million, EV is $40 million and AC is $45 million. All values are cumulative and use the same cost basis.
| Calculation | Result |
|---|---|
| Planned completion = 50 / 100 | 50% |
| Earned completion = 40 / 100 | 40% |
| Budget consumed = 45 / 100 | 45% |
| CV = 40 − 45 | −$5 million |
| SV = 40 − 50 | −$10 million |
| CPI = 40 / 45 | 0.889 |
| SPI = 40 / 50 | 0.800 |
The project has earned roughly 89 cents of budgeted accomplishment for each dollar incurred. It has delivered 80% of the budgeted work planned through the reporting date. Neither figure means the project is exactly 20% late in calendar time.
The question I would ask is whether the cost inefficiency and progress shortfall arise from the same work packages. If they do, a recovery plan that simply adds resources could improve production while making cost performance worse. If they do not, different interventions may be needed.
Establish the rules before accepting the results
Integrate scope, schedule and cost
The current SAE EIA-748E Earned Value Management Systems publication, Revision E dated February 17, 2026, identifies an integrated performance baseline and controlled baseline changes as core principles. SAE classifies it as an information report and describes scalability as a spectrum: the principles apply to all programs, while the detailed guidelines are aimed at large, complex or high-risk ones. That makes it a useful reference for owners, not a reason to impose a formal government-style compliance system on every construction contract.
I would require a work breakdown structure that connects the estimate to the schedule and identifies who owns each package. The budget should be distributed over the periods in which the work is planned, rather than allocated according to an invoice forecast. Each package needs a defined scope, measurable deliverables and a reporting owner.
Before accepting the baseline, I want to see that the schedule logic supports the contractual milestones, that the planned resources can deliver the work, and that the budget covers the defined scope. My article on scope baseline documentation addresses the broader scope discipline behind that process.
At the owner level, I also separate the performance measurement baseline from the total funding authorization. Unallocated contingency, financing costs or other expenditures that are not part of measured work should not be casually included in BAC. They belong in the appropriate reconciliations and owner funding forecasts. The Albers Management article on sizing, holding and releasing owner's contingency covers that reserve in detail.
Make progress measurable
Progress rules should be agreed before the reporting period begins. For repetitive installation, verified installed quantities may be appropriate. For engineering or procurement packages, weighted milestones can recognize discrete accomplishments. Short activities may use a completion-only rule. Time-based support activities should be identified separately rather than allowed to obscure discrete production performance.
For an equipment package, I might establish milestones for approved technical submittals, manufacturing completion, verified delivery, installation and successful acceptance testing. Each weight would reflect the budgeted effort or cost represented by that milestone. The weights must total the package budget and the same accomplishment cannot be counted twice.
I have reviewed progress reports in which an equipment package showed most of its value as earned because the equipment had been bought and paid for, while installation and testing, where the schedule risk sat, had barely started. The cost index looked healthy. The exposure simply did not appear in it. The fix was not a better chart. It was a milestone structure that gave honest credit for each stage and kept a meaningful share of the value for installation and acceptance.
An invoice, purchase order or deposit is not sufficient evidence of physical installation. Conversely, equipment legitimately earned through an approved procurement milestone should not be dismissed merely because it has not been installed. The distinction is whether the reported accomplishment matches the agreed measurement basis.
I expect the controls team to sample the supporting evidence. That can include inspection records, quantity takeoffs, approved deliverables and acceptance certificates. The verification should focus on high-value packages, unusual progress increases and activities driving contractual dates.
Preserve the history
Approved scope changes can legitimately change BAC and future planned value. They should be authorized, time-phased and traceable to a change register. A forecast change is not automatically a baseline change. Moving a planned activity into a later period simply because it has slipped removes the evidence needed to assess performance.
I want original and current approved baselines retained, with an explanation of every material movement. Where corrections to historical data are necessary, preserve the previously issued report and document the correction. Do not quietly reset the trend.
Read the trend before choosing a forecast
One month's CPI can be distorted by incomplete accruals, late progress certification or a change in the mix of work. A sustained pattern of unfavorable efficiency, supported by reliable quantities and costs, deserves more attention than an isolated ratio.
I review both current-period and cumulative performance. Cumulative numbers provide context but can mask recent deterioration. Period numbers expose changes faster but can be noisy. I want the package-level causes alongside both views, particularly when the remaining work differs substantially from what has already been completed.
The GAO guide recommends plotting current and cumulative EVM data, including cumulative and current CPI and SPI (page 259). Its discussion of forecast efficiency factors concludes that no single factor is superior and that the best one changes by the stage of the program (Table 24, pages 265 and 266). It also cites research that once a program is 20 percent complete, the cumulative CPI does not vary much from its value (less than 10 percent) and most often tends to get worse as completion grows nearer (pages 266 and 267). That research comes from defense programs, not ordinary building projects. I treat it as a reason to take an adverse CPI seriously once meaningful work is complete, not as a prediction for any particular project.
Estimate at completion: make the assumption visible
Estimate at completion (EAC) is the projected final cost of the measured scope. Estimate to complete (ETC) is the cost still expected to be incurred. Using the same hypothetical example, the remaining budgeted work is $60 million.
| Forecast approach | Formula | Illustrative EAC |
|---|---|---|
| Remaining work delivered at budgeted efficiency | AC + (BAC − EV) | $105.00 million |
| Cumulative cost efficiency continues | AC + (BAC − EV) / CPI | $112.50 million |
| Cost and schedule inefficiency both influence remaining cost | AC + (BAC − EV) / (CPI × SPI) | $129.38 million |
| Bottom-up reassessment of remaining work | AC + independently estimated ETC | Depends on ETC |
My cost control article covers the budgeting discipline behind these forecasts. The first forecast assumes the historical cost loss will not recur. I would accept that assumption only if the cause has been isolated and resolved. The second assumes the remaining work resembles past performance sufficiently for cumulative CPI to be informative. Under that assumption, BAC / CPI gives the same result.
The third is a sensitivity case for work where schedule inefficiency is reasonably expected to increase remaining costs. It is not automatically a worst-case forecast. Applying it mechanically to every package can overstate or double count schedule effects, especially where delay costs are already included elsewhere.
A bottom-up forecast is particularly useful when the remaining scope, resources or procurement exposure has changed materially. I expect it to incorporate remaining quantities, realistic rates, commitments, productivity, rework and time-related costs, as applicable. The statistical forecasts are independent checks, not substitutes for that assessment.
The difference between BAC and EAC is variance at completion (VAC = BAC − EAC). The cost-efficiency forecast above produces a negative $12.50 million VAC. These are conditional projections, not probability bounds or a forecast of the owner's total capital expenditure.
TCPI: challenge the recovery story
The to-complete performance index (TCPI) calculates the efficiency required on remaining work to achieve a target cost. For a target of BAC, it is (BAC − EV) / (BAC − AC). For an alternative target EAC, replace BAC in the denominator with that EAC.
In the example, meeting BAC requires 60 / 55 = 1.091. That is roughly 22.7% higher than the achieved CPI of 0.889, calculated using unrounded values. Meeting the $112.50 million forecast requires 60 / 67.50 = 0.889.
I would ask what specific operational changes justify the improvement needed to meet the original budget. A positive answer should identify changes in production rates, staffing, procurement or execution methods, with credible evidence. If no change supports the required efficiency, the target is an aspiration rather than a forecast.
I have sat through recovery presentations in which the required efficiency on the remaining work was well above anything the project had achieved to date, and the only change identified was increased management focus. That is not a plan. I ask what will be physically different on site next month: crews, sequence, material availability or method. If the remaining budget is zero or negative while work remains, TCPI is undefined or negative, and the target cannot be met at any level of efficiency.
Know what earned value cannot tell you
Traditional SPI has a mathematical limitation. When a late project finishes all its baseline scope, EV and PV both equal BAC, so SPI returns to 1.0 and SV becomes zero. PMI's published earned schedule paper explains this behavior and why conventional SPI becomes unsuitable for forecasting after the planned finish.
Earned Schedule addresses this particular limitation by locating the point in baseline time corresponding to current cumulative EV. If ES is that earned duration and AT is elapsed actual time from the baseline start, the time-based measures are SV(t) = ES − AT and SPI(t) = ES / AT. A positive elapsed duration is required for the ratio.
I would use those measures as a complement to, not a replacement for, the critical path method (CPM). Budget-weighted progress can be favorable while a relatively inexpensive activity controls the completion date. The owner still needs an updated logic-linked schedule, critical and near-critical paths, float movement and milestone forecasts. For the broader scheduling discipline, see Schedule Control: Building Predictability Into Every Project.
Front-loaded claims create another risk. I want milestone weights tested against the underlying budget and delivery risk, not accepted because the aggregate curve looks reasonable.
Finally, contractor CPI is not necessarily owner CPI. On a fixed-price contract, the contractor's internal cost overrun may initially reduce its margin rather than increase the owner's contract price. Claims, changes, default risk and delays can still affect owner exposure. Where internal cost data are unavailable, label owner payments and earned contract value as payment or commercial measures; do not present their ratio as contractor production-cost efficiency.
What I would require in the monthly reporting package
The reporting requirements should be established contractually and scaled to the project's risk and complexity. I would ask for the following information in a consistent format, with a common status date and a reconciliation to source systems.
| Reporting item | Owner's purpose |
|---|---|
| Baseline and current-period/cumulative PV, EV and AC by package | Identify where production and spending diverge |
| CV, SV, CPI and SPI trends | Distinguish persistent issues from reporting noise |
| Actual-cost reconciliation, accruals and commitments | Identify timing distortions and future liabilities |
| Baseline change log and progress evidence | Protect the integrity of the measurement |
| EAC, ETC, VAC and TCPI, with assumptions | Challenge the affordability of the remaining work |
| Updated critical path and milestone forecasts | Identify delivery dates at risk |
| Owner funding reconciliation and risk register | Separate performance exposure from total capital exposure |
| Corrective actions, accountable leads and decision dates | Establish responsibility for recovery |
I also want the underlying schedule and cost data in a usable format. A presentation is not sufficient if the team cannot reconcile the numbers or explain the calculation basis. Commitments should stay visible but distinct from incurred cost, and accruals should capture work performed but not yet invoiced without counting it twice when invoices arrive.
In the monthly review, I concentrate on what changed since the last report, whether performance or accounting timing drove it, and whether the same problem appears across several packages. Then I ask which milestone is now threatened and what decision the owner must make.
I prefer agreed escalation thresholds based on package size, risk and trend persistence rather than a universal red-amber-green rule. A small variance on a critical commissioning activity can justify faster action than a larger variance on noncritical work. Every corrective action should have a named owner and a measurable expected result for the next reporting cycle.
The purpose is earlier decisions
I do not expect an owner to become an earned value specialist. I expect the owner to understand what is being measured, recognize when the assumptions no longer hold, and demand an evidence-based plan for the work that remains.
Earned value earns its place in project governance when it changes a decision before the financial or schedule consequences become unavoidable. If the reporting process only confirms an overrun after the money is spent, the owner has missed its most useful purpose.
Related from Albers Management:
Forecasting & Trending: Seeing Around Corners – Albers Management
Owner's Contingency on Capital Projects: How to Size It, Hold It, and Release It – Albers Management
Reporting & Governance: Building Boardroom-Ready Confidence – Albers Management
Sources
- U.S. Government Accountability Office, Cost Estimating and Assessment Guide: Best Practices for Developing and Managing Program Costs, GAO-20-195G, March 2020. Chapter 19: Table 23 (p. 257), trend plots (p. 259), Table 24 and discussion (pp. 265-267). gao.gov (PDF)
- SAE International, Earned Value Management Systems, EIA748E (Information Report), revised February 17, 2026. saemobilus.sae.org
- Anbari, F.T., "The earned schedule," paper presented at the PMI Research and Education Conference, Limerick, Ireland, July 2012. Project Management Institute. pmi.org
All dollar figures in the worked example are illustrative, hypothetical figures, not a client result. First-person examples are drawn from the author's experience and generalized; no client, employer or project is identified.
About the Author
David Gray is a capital delivery strategist, owner's representative, and founder of DavidGrayProjects.com. With over two decades of experience helping organizations bring complex projects to life, from data centers and healthcare facilities to higher-ed campuses, David blends practical delivery with forward-thinking strategy.
He writes about project controls, capital planning, and real estate development to help leaders deliver smarter, faster, and more sustainably.
📩 Connect on LinkedIn | 🌐 Explore More at DavidGrayProjects.com | 🌐 Explore More at Albers Management